VERNON, Vt. — A key component of a plan to buy the shuttered Vermont Yankee nuclear power plant — which revolves around the early transfer of highly radioactive spent nuclear fuel — could be helped by a new canister design that hasn’t been approved yet by federal regulators.
If the new “proto-prompt” design by Holtec is approved, it could help Entergy empty the spent fuel pool years ahead of its original schedule.
The new Holtec design, which it is calling a “basket,” has 10 times the thermal cooling capacity of the design currently in use at Vermont Yankee, according to the latest information the company provided to the Nuclear Regulatory Commission about the new system.
A condition of the proposed sale to NorthStar Group Services calls for all 3,000 fuel rods to be removed from the spent fuel pool and placed in steel and concrete casks, where they will remain for decades, if not centuries.
NorthStar would then purchase Vermont Yankee from Entergy for $1,000 and get the plant’s $561 million decommissioning trust fund, with the condition that it immediately start cleaning up and tearing down the nuclear reactor.
The fuel, once it is stored in the canisters, would remain in Vernon until the Department of Energy either builds or approves a waste-storage site for highlevel radioactive fuel.
NRC spokesman Neil Sheehan said that while a five-year general rule had been in place between the time of a plant’s permanent shut down and the clean out of the spent nuclear fuel, he said that the nuclear makeup of the fuel and its age were important factors in determining the ability to move the fuel out of wet cooling to dry storage.
Entergy is currently using the Holtec “Hi-STORM” canister, spokesman Marty Cohn said Monday, but the company said last week it is asking the NRC for an unspecified amendment that it said would support the accelerated loading schedule.
Holtec, which is based in Ohio and is one of only a handful of companies that make nuclear storage canisters, has asked the NRC for amendments to the current system in use at Vermont Yankee.
Sheehan said that Holtec hasn’t yet received regulatory approval for the new design.
“Most certificates of compliance for dry-cask storage casks require that the spent fuel be cooled for at least five years in a plant’s circulating-water spent fuel pool before the casks can be loaded. However, the minimum acceptable cooling time may be as short as three years,” Sheehan wrote in an email.
“Cooling time is not the only factor considered when deciding the timing of dry-cask loading,” he said. “The initial enrichment of the nuclear fuel also factors into determining the suitability of a spent fuel assembly for dry-cask storage, as does the condition of the fuel cladding, or the zirconium alloy tubes in which the enriched nuclear fuel pellets reside.”
Sheehan added, “The bottom line is that in order to load spent fuel into dry casks, the company must ensure that the spent fuel meets all of the required characteristics specified by the cask manufacturer and contained in the certificate of compliance issued to the manufacturer by the NRC. The amount of time the spent fuel has been cooling in the spent-fuel pool cannot be used as the sole deciding factor for determining whether or not a particular spent fuel assembly is a valid candidate for storage in a dry-cask system.”
Even before the North Star deal was announced in November, Entergy had started work on a $145 million project to build an addition to the existing fuel-storage facility, and to get ready to transfer the fuel.
As part of that process, Entergy tore down its north warehouse, which the NRC said Monday was done without any problems, according to the agency’s latest Vermont Yankee inspection report.
Last week, during a meeting of the Vermont Nuclear Decommissioning Citizens Advisory Panel, Entergy officials outlined the most recent timetable for transferring the fuel. Entergy had previously accelerated its schedule for moving the fuel by two years, and the NorthStar project has moved it up even further.
Now, Entergy says it wants to complete the transfer by 2018; the earlier target was 2020.
Joe Lynch, an Entergy spokesman, told reporters after the meeting that Entergy currently has 13 storage containers holding old Vermont Yankee fuel, and it had already received 12 of the eventual 45 new fuel-storage containers on site, waiting for them to be filled. There will be 58 giant canisters on site when all the fuel is moved out of wet storage.
Entergy has already transferred the oldest spent fuel out of the spent-fuel pool into cask storage. The first transfer happened in 2008, and another took place in 2011.