BRATTLEBORO, Vt. — Entergy Nuclear is a Yankee after all.
It is engaging in the New England tradition of holding an auction, with hopes of recouping some cash from $20 million worth of spare parts left over when the Vermont Yankee nuclear power plant shut down in 2014.
Potential bidders Tuesday perused the hundreds of lots for sale, laid out on pallets in a former Georgia-Pacific paper mill in Brattleboro about 10 miles away from the Vernon reactor. An online auction started Wednesday morning.
“There are more than 900 lots, and they probably include 20,000 to 30,000 parts,” said David Bauer, who came out of retirement to organize the sale for Entergy at the Riverside Industrial Center.
Bauer and Entergy spokesman Marty Cohn stressed that nothing that was being sold had ever been in the plant and thus wasn’t exposed directly to radioactivity.
Bauer said that for 25 years it was his job to maintain a warehouse full of spare parts for Vermont Yankee, parts that might be needed at the drop of a hat. Everyone’s priority, he said, was to keep the plant in good shape and running, 24/7.
“Now you have to sell it. It’s kind of heartbreaking,” said Bauer.
“For over the 42 years we’ve been operating and putting away inventory, contingency parts. All those things are old but new,” Bauer said, who came out of retirement to run Entergy’s “asset recovery program” at Yankee.
It doesn’t make sense to buy a $3 ball bearing in a single lot, he said, so instead you can buy 300 at a time.
He said nuclear companies, mechanics and curiosity seekers were perusing the items in preparation for the sale.
He and Cohn said that spare parts could be a treasure trove for an artist or sculptor, who could make a lot of interesting sculptures out of the Yankee spare parts.
“There are a lot of nuts and bolts,” Cohn said.
There is also plenty of practical, non-nuclear things, like lightbulbs, office supplies, a wheelbarrow, rakes and shovels, fire extinguishers, copper pipe, a couple of forklifts and a Bobcat.
Cohn said that any proceeds from the sale would go into Entergy’s pocket, not the Vermont Yankee decommissioning trust fund.
He said that the parts were purchased by Entergy and its predecessor, Vermont Yankee Nuclear Power Corp., and not the trust fund.
Chris Recchia, commissioner of the Department of Public Service, who has challenged Entergy’s withdrawals from the trust fund, said any revenue from the sale of the parts and equipment was Entergy’s.
“If they paid for this with their own money, and I’m sure they did, they are entitled to any funds that come back in the auction,” Recchia said. “Clearly, the parts are not needed any more.”
Bauer hired a professional auction company, Heritage Global Partners, to do all the heavy lifting, and to sort all the different parts and equipment into similar lots. He said the company had done a similar sale at the Crystal River nuclear power plant in Florida.
The Vermont Yankee auction started Wednesday morning and concludes this evening, Bauer said.
“You can buy everything from an O-ring to a valve,” he said. “These things have never been in the plant itself.”
Nuclear pipe valves, which are anywhere from 12 to 18 inches in diameter, might have a limited use, he said, but the alloy and stainless steel in the valves would be valuable, Bauer said.
An entire pallet of baking soda was on hand to help neutralize any spills of battery acid.
On the Web: bit.ly/YankeeSale