CONWAY — While the Planning Board held off on taking a vote on the proposed cell tower on Route 116 to iron out conditions, members did signal their intention to approve the tower if they can reach agreeable terms with Vertex Tower Assets LLC.
The Wrentham-based company, which has several other towers built or approved in Franklin County, is proposing a 156-foot cell tower that requires special permit approval from the Planning Board and a variance from the Zoning Board of Appeals because Conway’s bylaws limit wireless towers to 120 feet. If approved, the tower would be built at 1356 Ashfield Road (Route 116) and would provide cell coverage on the state route into the center of town and parts of Ashfield.
The Planning Board closed the public comment of the permit application at its last meeting in May and members spent Thursday night deliberating on the application. The board’s main concern was ensuring that construction of the tower can only begin if Vertex has a licensed cell carrier ready to lease out a spot on the tower. Chair Beth Girshman initially wanted to set a condition that Vertex find two carriers before construction begins, but company owner Stephen Kelleher said that would be a tall order, “especially in these rural markets.”
“It’s hard to get $2 billion companies to come together on the same cycle,” Kelleher said. “It would be extremely unlikely to have two tenants out of the gate.”
Once constructed, the tower could accommodate four carriers, which Girshman said would be a concern if Vertex were unable to find four companies to sign on.
“This would be a worst-case scenario if we permit a tower that’s 150 feet tall because there’s four carriers, and there’s less and less chance for four carriers to come in,” Girshman said. “It’s a concern to me.”
While Kelleher said it would be difficult to find two carriers to sign on before construction begins, he said he “would never build a site without a tenant because there’s no benefit in doing it.” He noted Vertex would be paying construction and maintenance costs for a tower that is not providing a service.
“It doesn’t expedite anything for me to have a tower in the air with no tenant,” Kelleher said. “I would agree to one (carrier).”
Other conditions the Planning Board discussed include working out an agreement between the town, landlord and Vertex for decommissioning the tower when it is out of service and clarification of a specific “no cut zone” for vegetation and trees. Additionally, the town is asking Vertex to clarify whether the tower is a monopole or monopine tower. The special permit application designates it as a monopine tower, but Vertex’s team has been referring to it as a monopole structure. A monopine tower, designed to look like a pine tree, was used in Ashfield as the tower was more easily visible.
“I think in Ashfield, (a monopine) was appropriate,” Kelleher said, noting a monopole is more suited to the forested location in Conway. “For this one, it didn’t seem like it was heavily visible. … This one is a monopole and the drawing should depict a monopole as well.”
The land where the tower will be constructed in Conway must also comply with the Wetlands Protection Act.
The Planning Board will hold final deliberations and a vote on the tower at its next meeting on July 7. While a meeting was posted for the Zoning Board of Appeals to discuss the variance on Friday morning, it was ultimately canceled because the Planning Board did not render a decision. ZBA Chair Mark Silverman said the board will reconvene sometime around the Planning Board’s July 7 meeting and will consider the variance then.