Last year, Frank “Bud” Foster donated to Bernardston his property at 12 Church St., in the foreground, which is adjacent to the present Fire Station, to use for a Fire Station addition. The four-bay garage would be built on this lot separate from the existing station, though it would be attached by an enclosed walkway.
Last year, Frank “Bud” Foster donated to Bernardston his property at 12 Church St., in the foreground, which is adjacent to the present Fire Station, to use for a Fire Station addition. The four-bay garage would be built on this lot separate from the existing station, though it would be attached by an enclosed walkway. Credit: Staff File Photo/Paul Franz


BERNARDSTON — Members of the Selectboard and Fire Department will meet Tuesday at 5:30 p.m. to review a new Fire Station design plan after architect Brian DeVriese made changes based on firefighters’ suggestions last month.

“One of the biggest changes will be that the offices will be on the Church Street side of the building,” Town Coordinator Louis Bordeaux said. “It’s actually pretty exciting because it’s going to give the building more of a finished look, rather than just a red box.”

Firefighters had expressed that including updated office space in the new design is a priority. This addition has raised the potential costs from roughly $1.9 million to about $2.4 million, Bordeaux said. A more detailed cost breakdown will likely be reviewed during Tuesday’s meeting.

“We want the firefighters to look and see if it’s a workable design,” Bordeaux said.

After this review, the Selectboard will distribute information on the design plan updates to residents through the Greenfield Recorder, Bernardston town newsletter and posts on the town website. During a meeting this week, Selectboard member Brian Kier said the plans that had been presented through the December 2020 town newsletter were scrapped in place of the new design.

“What these plans will do is replace ones that went out already,” Bordeaux said. “When (the Selectboard) first decided to invite firefighters in for a conversation, the intent was not to change the plans. But the ideas they had were smart and workable.”

He also noted the town had money left that was originally budgeted for the architect’s design, so it did not cost any more than anticipated to ask for the redesign. While the addition to the project, which includes the office space, will cost about $400,000 more, Bordeaux said it also makes the building more serviceable.

The original plan was to build a garage bay for the Fire Department’s vehicles, with plans to keep offices in the existing station and renovate that as a separate project. Ultimately, town officials decided to include office space as part of the new station design after it was determined the cost of separate projects would be comparable to including office space in the new building.

With this updated design, an addition to the front side of the building facing Church Street would now include a foyer, a dispatch office, the fire chief’s office and a conference room. In an email to the town, DeVriese said he made the front office larger than the chief’s office to accommodate dispatch, reception and possibly an Emergency Operations Center if that is desired. The back half of the building would include garage bays for up to four vehicles, a shower room, a laundry room and a tool room.

The new building will be built on the lot at 12 Church St., on the west side of the existing station. Last spring, Frank “Bud” Foster, who died on Jan. 24, donated that property, which neighbors the current Fire Station lot, to the town to use as part of the new station’s grounds.

The new and existing stations would be connected by a covered, ramped hallway. During a February meeting, members of the Fire Department proposed putting storage lockers for turnout gear in this hallway space. However, DeVriese said in an email to the town that because the connector between the buildings is really a ramp, it would not work as a storage area for turnout gear. He explained this is a ramp because the floor elevation of the new building will be 2 feet higher than that of the existing station to make drainage work.

“I think we’ve come up with a plan that we’re going to take forward and see where it goes,” Selectboard Chair Stanley Garland said during this week’s board meeting. “We’re not the boss, the townspeople are the boss. Everybody’s got to understand that. Once they give us a direction, that’s the direction that we’ll follow.”

If the new design and cost estimate from DeVriese is viewed favorably, Garland has said town officials will move forward with the plan and present it to Bernardston residents, with hopes of holding a Special Town Meeting to vote on the proposal later this year.