CONWAY — Voters at Monday’s Special Town Meeting gave their blessing to borrowing nearly $1 million for a new highway maintenance building, though that decision is contingent on an affirmative debt exclusion vote set for Thursday.

Residents agreed to raise and appropriate or transfer from available funds $988,000 for the building. They also voted to transfer $50,000 from free cash to the general fund, and $433,243.51 from the Highway Garage Stabilization account to the general fund to partially finance the facility. The $433,243.51 is what remains in the stabilization account.

The 4,600- to 4,800-square-foot maintenance building, slated to sit next to Conway Grammar School, behind the salt shed, will have a maintenance bay, a wash bay, an office, a break room and a utility room, according to Town Administrator Tom Hutcheson. He and Highway Superintendent Ron Sweet said they hope the building will be finished by the end of 2020.

Hutcheson said the borrowing will now go out to bid to various banks and the town will go with the one with the lowest interest rate.

Sweet said the maintenance building will be used to work on Highway Department trucks and other equipment, and to wash them. He and Hutcheson said the Highway Department’s trucks and equipment will be kept in a 7,500-square-foot storage shed being built by Kurtz Inc. of Westfield and expected to be finished by January.

Voters twice rejected a garage proposal in 2014.

Polls will be open at Conway Town Hall from 11 a.m. to 7 p.m. on Thursday for the debt exclusion vote.

Voters on Monday also opted to pay $4,000 for legal assistance in negotiating a long-term contract with Comcast for the provision of cable services and $50,000 to provide a 40 percent match for a state grant to construct a lift for Town Hall.

Reach Domenic Poli at: dpoli@recorder.com or 413-772-0261, ext. 262.