WENDELL — The Planning Board is expected to make a decision next month on an application to amend a special permit for a Lockes Village Road solar array.
After four hours of discussion on Tuesday, Planning Board members said that they felt ready to discuss conditions for approval, pending legal advice from town counsel on whether the board could incorporate the Board of Health’s suggestion to require applicant Nexamp, doing business as Wendell Solar LLC, to conduct a hydrogeology study.
The board’s reconsideration of the previously approved project comes as Nexamp is looking to modify the site plan to reduce the original 100-foot natural buffer to 50 feet, as well as add detention and infiltration basins on the east side of the 14-acre parcel.
“Because cutting in half the protective buffer alters the approved footprint and increases off-site risks, while the applicant refuses to provide baseline groundwater data, the Board of Health urges you to deny this as a minor modification and require a new special permit application, subject to peer-reviewed, hydrogeologic testing, and current town bylaws and regulations,” Board of Health Chair Amy Simmons said.
Mike Cucchiara, senior vice president of business development at Nexamp, said that while Wendell Solar LLC has the backing of a larger company, each project has to “stand on its own” financially. Maintaining the 100-foot buffer would require more trees, which would in turn cast more shade over solar panels and would increase the risk of damage to the equipment. He added that the company is willing to pay for water quality testing for the directly abutting wells and the well for the Wendell Country Store, both before and after construction. However, he said he would argue against the hydrogeologic study, as the company already knows which direction the water flows in. He added that the addition of detention and infiltration basins should help improve water recharge.
“We are pushing back on this hydrogeologic study and it’s not because we’re an evil company out to destroy the environment,” Cucchiara said. “I know many people in the room believe that, and I understand the concern. This is water for your life, your home, your family. I think you’re being misled and taken down a rabbit hole.
“This is a bar beyond what we have ever encountered,” Cucchiara added.
“It doesn’t address all the concerns of the Board of Health,” Simmons said of Nexamp’s offer to conduct contaminant testing on wells.
Town Counsel Robin Stein with KP Law confirmed that, as this was a modification to a 2018 special permit, the Planning Board had to use the 2018 bylaws for its review. Stein noted that the changes, including reducing the buffer area with tree plantings, would not be considered a substantive change that would require a new special permit.
Nexamp had previously received a special permit to construct solar arrays on the Lockes Village Road property owned by Jake Doody. In the spring of 2025, the company requested a modification to the permit to allow for the addition of a battery energy storage system. Following pushback from abutters, that request was withdrawn. Now, the Planning Board must decide on a request to modify the permit to reduce the buffer zone from 100 feet to 50 feet, as well as add stormwater detention and infiltration basins.
Modifications to Nexamp’s plans include changes to the emergency management plan and improved fire safety. Fire Chief Matt O’Donnell explained that after a fire at a solar array in Shutesbury, he hopes to see fire protection “beefed up.” He noted he would like to see more winter maintenance, including plowing and sanding, as well as the installation of a smoke or heat alarm in the inverter.
“My understanding is basically the Shutesbury fire was a smoke investigation. They finally, after a half hour, figured out it was the inverter. Then they contacted NextEra [Energy], and then there was a delay in getting personnel on scene,” O’Donnell recounted. “So early notification, just like in your home, is key.”
Cucchiara said he has contacted the inverter supplier to discuss adding alarms, but the details are not finalized. He suggested that the Planning Board include a condition requiring the fire chief to sign off on the final emergency management plans before construction, as he does not believe he can add the alarms to the site plans before next month’s meeting.
He added that Nexamp plans to add an early warning alarm system, video monitoring and a 10-foot gravel perimeter around equipment. There would also be a 25-foot buffer between the solar panels and the perimeter fence to maintain access for brush trucks.
According to the Planning Board packet, if approval is secured, the company plans to begin site preparation in the fall of 2027. Construction would occur in late fall of 2027 and early winter of 2028, and the site would be ready for operation by April 2028.
Community members raise concerns
Abutters and community members engaged in spirited discussion on the project, and had to be reminded that discussion should be civil and focused on the special permit revision. Members of the Leverett Police Department, which provides policing services in Wendell through an inter-municipal agreement, joined the meeting after an aggressive, threatening sign was left on Doody’s property.
“Personal attacks have no place here at all. … We’re all longstanding citizens of this town and we care about this town,” Planning Board Chair Steve Gross said. “We’re all trying to figure out complicated processes.”
Neighbors echoed the Board of Health’s concerns and request for a hydrogeology study.
“There’s a whole lot of stuff that we don’t know about the water, about how it flows, about the potential impact to the water based on compaction and percolation of potentially toxic materials, and the consequences to both a public drinking supply and to our individual wells,” neighbor Ben Schwartz said. “Going in blind with the scant overview that was provided in the initial assessment done by Nexamp is not sufficient information.”
Glen Ayers, a registered sanitation professional assisting the Board of Health in its research and advocacy for the hydrogeology study, said that 100% of the residences in town rely on groundwater. He said that the Phase 1 report Nexamp submitted stated there was no indication of any issues with the water at the site, but no subsurface samples were taken.
“It is beyond prudent to at least characterize the site conditions,” Ayers said.
“I have concerns about my drinking water, as everyone does,” Selectboard member and neighbor Marina Apostol said. “Even the [U.S. Environmental Protection Agency] 2022 construction permit fact sheet … it specifically says construction, stormwater infiltration decisions should account for the site’s geology, groundwater depth and proximity to drinking water wells.”
“We hear the groundwater concerns,” Planning Board member Ray DiDonato said. “The question is what can and can’t we do legally.”
Gross said he contacted a few companies that could do a hydrogeology study based on the parameters of the Board of Health’s request and was told it could cost more than $100,000. He added that he was not sure that requiring the study would be considered “reasonable” if the decision were to go to court, and questioned what the purpose of the study would be.

“Most of them had no knowledge of any studies being done, or any examples of the kind of things we’re worried about happening,” Gross said. “One of the reasons that there aren’t many studies is that, in fact, there haven’t been enough problems for people to get a hold of and take a look at this.
“If there’s gonna be a problem, is this study gonna prevent a problem from occurring?” Gross continued.
Following discussion, board members agreed that they were ready to deliberate on the proposed special permit amendments and potential conditions for approval. They noted that they would be closing the public comment portion of the hearing and would not entertain public testimony on topics not related to the permit conditions.
The Planning Board is expected to continue discussion and potentially vote on the matter on Tuesday, Dec. 14, at 6:30 p.m. at the Wendell Town Offices.